Project Overview : High Voltage tower installation including civil work , tower erection and cable stringing Length : 127 Km /Voltage : 225 Kv Length : 274 Km /Voltage : 150 Kv Length : 375 Km /Voltage : 90 Kv…
Oct - 11
2017
Project Overview : High voltage tower installation (Lot 1 & 3) including civil work, tower erection and cable stringing Length : 220 KM /Voltage : 400 KV Length : 70 KM /Voltage : 225 KV Length : 150 KM /Voltage…
Oct - 11
2017
Project Overview : Construction of 225/400 KV Over head Power Transmission Line Interconnection between Tunisia & Libya Length : 336 Km / Voltage : 225 & 400 Kv Client : STEG Location : Sfax/Medenin Completion Date : 2001
Oct - 11
2017
Project Overview : High Voltage underground cable laying Length – Km : 69 / Voltage – Kv : 225 Length – Km : 64 / Voltage – Kv : 90 Client : STEG/ PIRELLI Location : Rades/Grombalia – Tunis/Rades/Bizerte
Oct - 11
2017
Project Overview : High Voltage underground cable laying Length : 4.7 Km/ Voltage : 225 Kv Length : 27 Km / Voltage : 225 Kv Client : STEG/ NEXANS-PRYSMIAN Location : Tunis/Goulette/Kram/Mnihla
Oct - 11
2017
Project Overview : Nawara Central Processing Facility including Gas & condensate pipelines interconnection and related facilities.Engineering, procurement, construction, commissioning & start-up of Nawara Central Processing Facility (In JV With MS Germany) including Gas & condensate pipelines interconnection and related facilities,…